Project Description:
DEERFIELD- BRIDGE REPLACEMENT, D-06-023, MCCLELLAN FARM ROAD OVER THE B&M RAILROAD
The purpose of this project is to replace the bridge structure with a 42 foot wide bridge. The approaching roadways will also be reconstructed and a sidewalk will be added on both side of the bridge. Also included in this project is the some minor reconstruction of and improvements to McClellan Farm Road and River Road. Some temporary easements will be required for the construction of slopes. The bridge will be closed and a detour will be provided to River Road.
Location:
  • Town of Deerfield
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Randal Machon
    Construction Bid Price: $5,055,968.36
    District: District 2

    Contracts (3) Progress
    # 58997 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 77853 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 96619 -- Construction Contract
    Bridge Replacement Br. No. D-06-023 (Steel) McClelland Farm Road over the Pan Am Railroad. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/06/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/27/1997
    Project Review Committee PRC Approved 10/07/1997
    Project Status Advertised 07/30/2016
    Project Management
    100% Design 100% Package Received 08/12/2015
    25% Design 25% Package Received 06/30/2014
    25% Design 25% Package Comments to DE 09/16/2014
    25% Design 25% Package Comments to DE 10/20/2014
    25% Design Design Public Hearing 11/18/2014
    75% Design 75% Package Received 03/23/2015
    Final Design PS&E Received 11/23/2015
    Final Design PS&E to FAPRO 07/25/2016
    Consultant Contract Process NTP Issued 07/01/2011
    Consultant Contract Process Workhours Approved 07/01/2011