AMESBURY- BRIDGE REPLACEMENT, A-07-015, R STREET OVER THE BACK RIVER
The proposed project consists of replacing the existing single span steel stringer bridge over the Back River in its present location. The proposed new single span concrete bridge will be founded on new abutments which will be constructed behind the existing abutments. Minor improvements to the approach roadway will be provided.
Location:
  • Town of Amesbury
  • Resident Engineer: Raymond Orsini
    Construction Contract Value: $1,543,602.00
    Construction Bid Price: $1,396,293.00
    Initial Construction Estimate: $1,666,128.00
    District: District 4

    Contracts (2) Progress
    # 58595 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 63128 -- Construction Contract
    Bridge Replacement (A-07-015) (Concrete) - "R" Street over the Back River. Terminated

    Bridges

    Contract Dates
    Notice to Proceed: 06/23/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/02/1997
    Project Review Committee PRC Approved 10/07/1997
    Project Status Advertised 02/13/2010
    Project Management
    100% Design 100% Package Received 02/06/2004
    100% Design 100% Package Comments to DE 07/13/2005
    25% Design 25% Package Received 05/09/2002
    25% Design 25% Package Comments to DE 11/20/2002
    25% Design Design Public Hearing 01/28/2003
    75% Design 75% Package Received 05/05/2003
    75% Design 75% Package Comments to DE 09/28/2003
    Final Design PS&E Received 02/21/2007
    Final Design PS&E Received 01/14/2009
    Final Design PS&E to FAPRO 09/17/2007
    Final Design PS&E to FAPRO 09/30/2009
    Consultant Contract Process Scope to DE 06/23/2000
    Consultant Contract Process NTP Issued 10/23/2000
    Consultant Contract Process Workhours Approved 09/19/2000