| Project Description: |
AMESBURY- BRIDGE REPLACEMENT, BR# A-07-004 THOMPSON STREET OVER THE POWWOW RIVER
The proposed project consists of replacement of the existing bridge on the same alignment with improvements to the approach roadway.
|
| Location: |
|
| Resident Engineer: | Bernard LaVita![]() |
| Construction Contract Value: | $924,731.00 |
| Construction Bid Price: | $787,937.50 |
| Initial Construction Estimate: | $527,198.00 |
| Total Estimated Project Cost: | $600,000.00 |
| District: | District 4 |
| Current Status: | Bridge is open to traffic. This project is complete. (as of 02/01/2007) |
|