Project Description:
PLYMPTON- RECONSTRUCTION OF ROUTE 58, MAIN STREET & PALMER ROAD
This proposed project includes the reconstruction of Route 58 to improve traffic operations and safety. This project is approximately 3 miles in length and includes the installation of a fully actuated traffic signal at the village center.
Location:
  • Town of Plympton
  • Resident Engineer: Ronald Strangfeld
    Construction Contract Value: $4,575,529.96
    Construction Bid Price: $3,434,156.30
    Initial Construction Estimate: $3,647,800.00
    District: District 5

    Contracts (1) Progress
    # 51784 -- Construction Contract
    Plympton - Roadway Reconstruction and Related Work on Route 58 (Main Street and Palmer Road) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/24/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 10/07/1997
    Project Review Committee Letter 10/23/1997
    Project Status Advertised 08/05/2006
    Project Management
    100% Design 100% Package Received 07/25/2005
    100% Design 100% Package Comments to DE 01/30/2006
    25% Design 25% Package Received 02/06/2003
    25% Design 25% Package Comments to DE 06/05/2003
    25% Design Design Public Hearing 10/16/2003
    75% Design 75% Package Received 05/03/2004
    75% Design 75% Package Comments to DE 01/25/2005
    Final Design PS&E Received 03/29/2006
    Final Design PS&E to FAPRO 07/17/2006