GILL- RECONSTRUCTIO OF MAIN ROAD, FROM NORTHFIELD TL SOUTHERLY TO WOOD AVENUE
This project involves the reconstruction of Main Road for a distance of 2.10 miles. Paved shoulders, new sidewalks, drainage improvements, guardrail, and landscaping will also be provided.
Location:
  • Town of Gill
  • Resident Engineer: Sean Burke
    Construction Contract Value: $4,281,585.00
    Construction Bid Price: $3,757,710.00
    Initial Construction Estimate: $3,484,609.00
    District: District 2
    Current Status: Road under construction (as of 09/05/2006)
    Additional Info: Daily lane restrictions/reductions during the work week. All lanes open at the end of the work day and weekends. (as of 03/25/2008)

    Contracts (1) Progress
    # 44255 -- Construction Contract
    Gill - Roadway Reconstruction Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/16/2006
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Road under construction
    Additional Info
    Daily lane restrictions/reductions during the work week. All lanes open at the end of the work day and weekends.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/18/1997
    Project Review Committee PRC Approved 10/07/1997
    Project Status Advertised 05/28/2005
    Project Status Advertised 09/30/2005
    Project Management
    100% Design 100% Package Received 04/25/2001
    100% Design 100% Package Comments to DE 08/27/2002
    100% Design 100% Plans Complete 04/01/2002
    25% Design 25% Package Received 02/23/1999
    25% Design Design Public Hearing 06/09/2000
    75% Design 75% Package Received 05/30/2000
    75% Design 75% Plans Approved 07/07/2000
    Final Design PS&E Received 04/12/2004
    Final Design PS&E Received 07/28/2004
    Final Design PS&E to FAPRO 08/05/2004