ANDOVER- RECONSTRUCTION OF ROUTE 28 (MAIN STREET), FROM WHEELER STREET TO THE SHAWSHEEN RIVER
The proposed 1.1 mile roadway reconstruction, from just north of School Street to the intersection of Main Street and North Street, extends from residential neighborhoods to the downtown business district, where high pedestrian concentrations will be enhanced with new pedestrian actuated signal systems, new handicapped ramps and bicycle accommodations. New traffic signals at major intersection will process traffic more efficiently. Other improvements include turning lanes, new street lighting, new trees and grates, benches, trash receptacles and bike racks in the downtown area.
Location:
  • Town of Andover
  • Resident Engineer: Bernard LaVita
    Construction Contract Value: $4,450,592.43
    Construction Bid Price: $3,871,336.20
    Initial Construction Estimate: $3,272,668.00
    District: District 4

    Contracts (1) Progress
    # 51849 -- Construction Contract
    Andover - Roadway Reconstruction on a Section of Route 28 (Main Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/03/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/23/1997
    Project Review Committee PRC Approved 10/07/1997
    Project Review Committee Letter 10/21/1997
    Project Status Advertised 06/24/2006
    Project Management
    100% Design 100% Package Received 01/05/2005
    100% Design 100% Package Comments to DE 09/30/2005
    25% Design 25% Package Received 01/04/2001
    25% Design 25% Package Comments to DE 07/30/2001
    25% Design Design Public Hearing 01/09/2002
    75% Design 75% Package Received 11/17/2003
    75% Design 75% Package Comments to DE 10/21/2004
    75% Design 75% Plans Approved 10/07/2004
    Final Design PS&E Received 12/29/2005
    Final Design PS&E to FAPRO 01/17/2006