Project Description: |
CHARLEMONT- BRIDGE REPLACEMENT, BR# C-05-026 SOUTH RIVER ROAD OVER BOZRAH BROOK
The purpose of this project is to replace the South River Road Bridge over Bozrah Brook on the same alignment with improvements to the approach roadway.
|
Location: |
|
Resident Engineer: | Thomas Tierney |
Construction Contract Value: | $1,535,713.00 |
Construction Bid Price: | $707,921.40 |
Initial Construction Estimate: | $528,455.10 |
District: | District 1 |
Current Status: | The final paving is complete and the roadway is open to traffic. (as of 05/31/2005) |
Additional Info: | (as of 06/09/2005) |
|
Bridges
|
|
|
|
|