Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- EVERETT- RECONSTRUCTION & SIGNAL IMPROVEMENTS ON ROUTE 99 (BROADWAY), FROM SWEETSER CIRCLE TO ALFORD STREET BRIDGE
The proposed reconstruction and signal improvements project on Route 99 (Broadway), from Sweetser Circle to Alford Street Bridge include: pavement overlays, minor drainage improvements, sidewalk and ramp accessibility improvements, and improvements to accommodate bicycles. Traffic signals will be upgraded at three intersections along Route 99; Beckham Street, Bowdoin Street and Dexter Street. Full depth pavement reconstruction will also be performed for the segment of Broadway between Bartlett Street and the Beacham Street.
Location:
  • City of Boston
  • City of Everett
  • Resident Engineer: Joseph Coleman
    Construction Contract Value: $3,720,546.00
    Construction Bid Price: $3,390,952.83
    Initial Construction Estimate: $4,360,665.00
    District: District 6

    Contracts (2) Progress
    # 58213 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 67945 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals) on a Section of Route 99 (Broadway). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/02/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/16/1997
    Project Review Committee PRC Approved 01/13/1998
    Project Status Advertised 09/18/2010
    Project Management
    100% Design 100% Package Received 03/12/2010
    100% Design 100% Package Comments to DE 05/11/2010
    25% Design 25% Package Received 08/31/2007
    25% Design 25% Package Received 12/04/2008
    25% Design 25% Package Comments to DE 05/08/2009
    25% Design Design Public Hearing 07/14/2009
    Final Design PS&E Received 08/31/2010
    Final Design PS&E to FAPRO 09/08/2010