Project Description: |
EVERETT- ROADWAY RECONSTRUCTION, TRAFFIC SIGNAL UPDATE, RTE 99 FROM Second Street to the Malden city line
The project involves full depth roadway reconstruction, roadway overlay, new sidewalks, and signalization improvements at 9 locations directly along and adjacent to Broadway.
|
Location: |
|
Resident Engineer: | Francis Goodhue |
Construction Contract Value: | $4,992,667.00 |
Construction Bid Price: | $4,073,770.12 |
Initial Construction Estimate: | $3,607,899.50 |
District: | District 4 |
Current Status: | All work is complete except punch list work . The final punch list has been received from consultant. The contractor and subcontractors are currently working on this final list. (as of 02/15/2008) |
|