DUXBURY- HINGHAM- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE 3
The work under this contract consists of cold planing, resurfacing, bridge work such as bridge joint repair and resurfacing on Route 3 in the towns of Duxbury, Pembroke, Marshfield, Norwell, Hanover, Rockland and Hingham for a distance of 14 miles. Other incidental work includes drainage structure repairs, guard rail end treatment replacements, and pavement markings.
Location:
  • Town of Duxbury
  • Town of Hingham
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: Other
    Project Manager: Brian Haggerty
    Estimated Total Contract Cost: $7,890,869.22
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project