Project Description:
BELCHERTOWN- PELHAM- RESURFACING AND RELATED WORK ON ROUTE 202
The project begins just north of Maple Street at the Belchertown Town Common and proceeds northerly on Route 202 to Packardville Road in Pelham for a total distance of approximately 5.2 miles. The intersection of Route 9 and 202 is not included in this project. Other work to be done includes cold planing, replacing and/or constructing new drainage structures and pipes, relining a failing culvert, installing sub-drain, pavement markings, snowplowable raised pavement markers, tree trimming, traffic control, cleaning drainage structures and pipes, erosion/sedimentation control measures, and other incidental items.
Location:
  • Town of Belchertown
  • Town of Pelham
  • Resident Engineer: Dennis Murphy
    Construction Contract Value: $2,600,878.00
    Construction Bid Price: $2,251,063.56
    Initial Construction Estimate: $2,670,790.00
    District: District 2
    Current Status: Road under construction (as of 04/01/2008)
    Additional Info: Daily lane restrictions/reductions during the work week. All lanes open at the end of the work day and weekends. (as of 05/01/2008)

    Contracts (1) Progress
    # 53919 -- Construction Contract
    Work consists of resurfacing and related work on a section of Route 202 in Belchertown and Pelham. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/13/2008
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Road under construction
    Additional Info
    Daily lane restrictions/reductions during the work week. All lanes open at the end of the work day and weekends.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/01/1997
    Project Review Committee PRC Approved 01/13/1998
    Project Status Advertised 09/15/2007
    Project Management
    75% Design 75% Package Received 01/09/2006
    Final Design PS&E Received 09/05/2007
    Final Design PS&E to FAPRO 09/10/2007