HOLYOKE- RECONSTRUCTION OF COMMERCIAL STREET
This project consists of the full depth roadway reconstruction of 0.6 miles of Commercial Street, Nick Cosmos Way and a portion of Appleton Street in the City of Holyoke. The project also includes the cold planing and resurfacing of portions of Jackson Street, Franklin Street, Hampshire Street, Sergeant Street, Essex Street, Bristol Place, and Hertitage Street. In addition, the project includes the construction of a new drainage system in order to separate combined sewer and drainage lines within the project limits.
Location:
  • City of Holyoke
  • Resident Engineer: Joseph Hogan
    Construction Contract Value: $3,403,487.00
    Construction Bid Price: $3,379,419.20
    Initial Construction Estimate: $3,079,815.00
    District: District 2

    Contracts (1) Progress
    # 43312 -- Construction Contract
    Ludlow - Reconstruction and Related Work on Commercial Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/09/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/26/1997
    Project Review Committee PRC Approved 01/13/1998
    Project Status Advertised 05/07/2005
    Project Management
    100% Design 100% Package Received 07/09/2004
    100% Design 100% Package Received 08/02/2004
    100% Design 100% Package Comments to DE 08/04/2004
    100% Design 100% Plans Complete 08/10/2004
    25% Design 25% Package Received 12/14/1998
    25% Design 25% Package Comments to DE 03/10/1999
    25% Design Design Public Hearing 02/10/1999
    75% Design 75% Package Received 11/24/1999
    75% Design 75% Package Comments to DE 02/02/2000
    75% Design 75% Plans Complete 05/09/2000
    Final Design PS&E Received 08/13/2004
    Final Design PS&E to FAPRO 08/13/2004