| Project Description:
|
LITTLETON- MILLBURY- OXFORD- STERLING- WESTFORD- WESTMINSTER- CONSTRUCTION OF 6 CHEMICAL STORAGE SHEDS AT DEPOTS
|
| Location:
|
Town of Littleton
Town of Millbury
Town of Oxford
Town of Sterling
Town of Westford
Town of Westminster
|
| Design Responsibility:
|
In-House Boston |
| Right of Way Responsibility:
|
Other |
| Project Manager:
|
Gerald Donnellan |
| Estimated Total Contract Cost:
|
$1,116,000.00 |
| Estimated Total Federal Participating Construction Cost:
|
N/A |
| District:
|
District 3 |
| Current Status:
|
This project is in the preliminary design phase. |