Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LITTLETON- MILLBURY- OXFORD- STERLING- WESTFORD- WESTMINSTER- CONSTRUCTION OF 6 CHEMICAL STORAGE SHEDS AT DEPOTS
Location:
  • Town of Littleton
  • Town of Millbury
  • Town of Oxford
  • Town of Sterling
  • Town of Westford
  • Town of Westminster
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: Other
    Project Manager: Gerald Donnellan
    Estimated Total Federal Participating Construction Cost: $500,000.00
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 04/21/2001 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/24/1997
    Project Review Committee PRC Approved 01/13/1998
    Project Status Advertised 04/21/2001
    Project Management