| Project Description: |
ROYALSTON- BRIDGE REPLACEMENT, BR# R-12-012 DELAND ROAD OVER PRIEST BROOK
The proposed project consists of replacing the Deland Road bridge over Priest Brook in its former location with minor improvements to the approach roadways. The bridge formerly located on the site was removed in 1995.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | Municipality |
| Project Manager: | Martin Leelman![]() |
| Estimated Total Federal Participating Construction Cost: | $209,000.00 |
| District: | District 2 |
| Current Status: | This project has been advertised for construction bids. (as of 09/28/2002 ) |
|