Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ROYALSTON- BRIDGE REPLACEMENT, BR# R-12-012 DELAND ROAD OVER PRIEST BROOK
The proposed project consists of replacing the Deland Road bridge over Priest Brook in its former location with minor improvements to the approach roadways. The bridge formerly located on the site was removed in 1995.
Location:
  • Town of Royalston
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Project Manager: Martin Leelman
    Estimated Total Federal Participating Construction Cost: $209,000.00
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 09/28/2002 )

    Contracts (1) Progress
    # 95253 -- Design -- Bridge Open End
    OFF SYSTEM FAID BR-RND 4 CONTB Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/02/1997
    Project Review Committee PRC Approved 01/13/1998
    Project Status Advertised 09/28/2002
    Project Management