BUCKLAND- BRIDGE REPLACEMENT, BR# B-28-011, UPPER STREET OVER THE CLESSON BROOK
This project will result in the demolition and replacement of the existing bridge superstructure with pre-stressed concrete deck beams. The new superstructure will be supported on the existing abutments.
Location:
  • Town of Buckland
  • Resident Engineer: Thomas Tierney
    Construction Contract Value: $648,548.00
    Construction Bid Price: $558,680.00
    Initial Construction Estimate: $466,975.00
    Total Estimated Project Cost: $500,000.00
    District: District 1
    Current Status: Bridge is open to traffic. Work continues on punch list. (as of 08/22/2005)

    Contracts (1) Progress
    # 36203 -- Construction Contract
    Buckland-Bridge Replacement B-28-011 Upper Street over Clesson Brook Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/29/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge is open to traffic. Work continues on punch list.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/03/1997
    Project Review Committee PRC Approved 01/13/1998
    Project Status Advertised 05/01/2004
    Project Management
    100% Design 100% Package Received 05/05/2000
    100% Design 100% Package Comments to DE 05/30/2000
    25% Design 25% Package Received 02/16/1999
    25% Design 25% Package Comments to DE 03/23/1999
    75% Design 75% Package Received 08/19/1999
    75% Design 75% Package Comments to DE 09/15/1999
    Final Design PS&E Received 02/04/2004
    Final Design PS&E to FAPRO 02/04/2004