ADAMS- BRIDGE REHABILITATION, A-04-006, RIVER STREET OVER THE HOOSIC RIVER
The proposed work is to replace the existing River Street Bridge over the Hoosic River on the same alignment with improvements to the approach roadway. The bridge is safe for pedestrians, but is closed to vehicular traffic.
Location:
  • Town of Adams
  • Resident Engineer: Thomas Tierney
    Construction Contract Value: $521,549.00
    Construction Bid Price: $432,863.60
    Initial Construction Estimate: $286,670.00
    District: District 1
    Current Status: Project is complete. (as of 07/08/2008)

    Contracts (2) Progress
    # 51388 -- Construction Contract
    Adams - Bridge Superstructure Replacement (A-04-006) (Concrete) - River Street over the Hoosic River Completed
    # 96059 -- Design -- Bridge Open End
    RD 3 F/A NON-NHS BRIDGES-CON G Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/21/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/01/1997
    Project Review Committee PRC Approved 01/13/1998
    Project Status Advertised 07/01/2006
    Project Management
    100% Design 100% Package Received 12/23/2005
    100% Design 100% Package Comments to DE 03/07/2006
    75% Design 75% Package Received 01/24/2003
    75% Design 75% Package Comments to DE 04/17/2003
    Final Design PS&E Received 03/31/2006
    Final Design PS&E to FAPRO 04/05/2006