DRACUT- BRIDGE REHABILITATION, BR# D-11-007, LAKEVIEW AVENUE OVER CANAL OFF BEAVER BROOK (CULVERT)
The work involves the replacement of the existing culvert with a new precast concrete culvert. Approximately 60 feet of roadway will also be reconstructed.
Location:
  • Town of Dracut
  • Resident Engineer: Mark Fedele
    Construction Contract Value: $576,617.50
    Construction Bid Price: $544,397.50
    Initial Construction Estimate: $542,202.13
    District: District 4
    Current Status: Contract work is complete. Final Inspection was held 6/21/2006. (as of 09/18/2006)

    Contracts (1) Progress
    # 39899 -- Construction Contract
    Dracut - Culvert Replacement, Bridge #D-11-007, Lakeview Avenue over Inactive Canal Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/20/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contract work is complete. Final Inspection was held 6/21/2006.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/11/1997
    Project Review Committee PRC Approved 01/13/1998
    Project Status Advertised 08/07/2004
    Project Management
    100% Design 100% Package Received 04/09/2004
    100% Design 100% Package Comments to DE 07/16/2004
    25% Design 25% Package Received 05/28/2002
    25% Design 25% Package Comments to DE 11/05/2002
    75% Design 75% Package Received 07/18/2003
    75% Design 75% Package Comments to DE 12/03/2003
    75% Design 75% Plans Complete 03/03/2004
    Final Design PS&E Received 08/03/2004
    Final Design PS&E to FAPRO 08/03/2004