Project Description: |
LEOMINSTER- BRIDGE REHABILITATION, BR# L-08-002 ROUTE 13 (MAIN STREET) OVER THE NORTH NASHUA RIVER
The purpose of this project is to rehabilitate / strengthen the existing stone masonry arches and incorporate roadway and bridge safety improvements.
|
Location: |
|
Resident Engineer: | Stephen Romano |
Construction Contract Value: | $3,103,207.00 |
Construction Bid Price: | $2,745,097.50 |
Initial Construction Estimate: | $2,245,440.00 |
District: | District 3 |
Current Status: | The contractor has finished adjusting all the drainage and sanitary structures. Most of the areas that require loam and seed have been completed. Roadway paving is anticipated to occur soon. (as of 10/23/2008) |
|
Bridges
|
|
|
|
|