Project Description:
MERRIMAC- RECONSTRUCTION OF ROUTE 110 (WEST MAIN STREET/EAST MAIN STREET), FROM 400 FEET WEST OF ORCHARD STREET TO BROAD STREET
The proposed project will reconstruct a section of Route 110 (Downtown Main Street) in Merrimac. This project starts in the vicinity of Currier Avenue, continues easterly through the center of town, and ends immediately west of the Broad Street Intersection.
Location:
  • Town of Merrimac
  • Resident Engineer: Raymond Orsini
    Construction Contract Value: $5,034,339.00
    Construction Bid Price: $5,417,148.80
    Initial Construction Estimate: $5,795,127.00
    District: District 4

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69360 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 79596 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Route 110 (East Main & West Main Streets). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/17/1997
    Project Review Committee PRC Approved 01/13/1998
    Project Status Advertised 09/07/2013
    Project Management
    100% Design 100% Package Received 10/05/2012
    100% Design 100% Package Comments to DE 12/28/2012
    25% Design 25% Package Received 10/24/2002
    25% Design 25% Package Received 12/29/2008
    25% Design 25% Package Comments to DE 01/24/2003
    25% Design 25% Package Comments to DE 08/03/2009
    25% Design Design Public Hearing 07/13/2010
    75% Design 75% Package Received 05/06/2011
    75% Design 75% Package Comments to DE 02/03/2012
    Final Design PS&E Received 06/10/2013
    Final Design PS&E to FAPRO 08/28/2013