ANDOVER- 3 LOCATIONS ON ROUTE 125 (PROSPECT, VINE, WILDWOOD)
The proposed work is located at Rte. 125 (Andover Bypass) at the following cross roads: Prospect Rd, Vine St, and Wildwood Rd. The work includes full-depth roadway construction, minor roadway widening, cold planing and resurfacing, minor geometric improvements, retaining wall construction, installation of intersection control beacons at Prospect and Wildwood Roads, installation of granite edging and asphalt curb and berms, drainage improvements, landscaping, tree planting, signing, and pavement markings.
Location:
  • Town of Andover
  • Resident Engineer: Gregory Ramstine
    Construction Contract Value: $1,204,349.00
    Construction Bid Price: $1,071,136.00
    Initial Construction Estimate: $891,943.00
    District: District 4
    Current Status: All roadway work including paving and thermoplastic completed as of October 5, 2006. Traffic signal strain pole instllation is in progress. Traffic sign installation will be complete by late December 2006. (as of 12/20/2006)

    Contracts (1) Progress
    # 41188 -- Construction Contract
    Traffic Signal Improvements, Andover - Rte. 125 (3 Locations) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/22/2005
    Contract Information
    Project Designer: Other
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    All roadway work including paving and thermoplastic completed as of October 5, 2006. Traffic signal strain pole instllation is in progress. Traffic sign installation will be complete by late December 2006.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/25/2004
    Project Management
    25% Design Design Public Hearing 03/21/2000
    Final Design PS&E Received 09/17/2004
    Final Design PS&E to FAPRO 09/17/2004