Project Description:
FALL RIVER- RECONSTRUCTION OF MERIDIAN STREET, FROM WILSON ROAD TO RUTH STREET (3.3 KM)
The project consists of the reconstruction of Meridian Street from north of Hannah Street to Wilson Road (near the North End Elementary School), for a distance of approximately 1.86 miles along the existing alignment. The project includes pavement reclamation and full depth widening and sidewalk and wheelchair ramp installation on the westerly side of Meridian Street and for a limited portion of the project at the northerly end. The project also includes associated resetting and installation of curbing, minor drainage improvements, signs and pavement markings, and utility pole relocations.
Location:
  • City of Fall River
  • Resident Engineer: David Ribeiro
    Construction Contract Value: $3,178,014.34
    Construction Bid Price: $2,483,993.49
    Initial Construction Estimate: $2,868,961.00
    District: District 5

    Contracts (1) Progress
    # 53366 -- Construction Contract
    Fall River - Roadway Reconstruction and Related Work on a Section of Meridian Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/22/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Tabled 04/14/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Review Committee Letter 10/01/1998
    Project Status Advertised 09/23/2006
    Project Management
    100% Design 100% Package Received 04/14/2006
    100% Design 100% Package Comments to DE 06/08/2006
    25% Design 25% Package Received 12/23/2003
    25% Design 25% Package Comments to DE 12/07/2004
    25% Design Design Public Hearing 12/15/2004
    25% Design 25% Plans Complete 07/25/2005
    75% Design 75% Package Received 10/28/2005
    75% Design 75% Package Comments to DE 03/01/2006
    75% Design 75% Plans Complete 01/17/2006
    Final Design PS&E Received 07/26/2006
    Final Design PS&E Received 12/18/2006
    Final Design PS&E to FAPRO 09/13/2006