Project Description:
FALL RIVER- HIGHWAY RECONSTRUCTION, NORTH MAIN ST. FROM INTERSECTION OF HERMAN ST. NORTHERLY DIR. TO FREETOWN TL
The proposed project consists of the reconstruction of North Main Street from Herman Street to the Freetown Town Line with minor widening. The project includes the construction of new sidewalks with wheelchair ramps, existing granite curb and new pavement.
Location:
  • City of Fall River
  • Resident Engineer: David Ribeiro
    Construction Contract Value: $2,894,631.17
    Construction Bid Price: $2,150,648.07
    Initial Construction Estimate: $2,248,073.49
    District: District 5

    Contracts (1) Progress
    # 38381 -- Construction Contract
    Fall River - Roadway Reconstruction on a Section of North Main Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/08/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/29/1997
    Project Review Committee PRC Tabled 04/14/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 08/28/2004
    Project Management
    100% Design 100% Package Received 04/23/2004
    100% Design 100% Package Comments to DE 07/27/2004
    100% Design 100% Plans Complete 09/01/2004
    25% Design 25% Package Received 07/15/2001
    25% Design 25% Package Comments to DE 06/05/2003
    75% Design 75% Package Received 07/28/2003
    75% Design 75% Package Comments to DE 01/22/2004
    Final Design PS&E Received 07/22/2004
    Final Design PS&E to FAPRO 07/22/2004