Project Description:
GRAFTON- BRIDGE REPLACEMENT, BR# G-08-012 DEPOT STREET OVER PROVIDENCE & WORCESTER RAILROAD
The work shall include full demolition of the existing wooden bridge, construction of the proposed 3-span steel bridge superstructure and substructure, construction of wingwalls, installation of bridge rail and guardrails, and other incidental bridge work. The work shall also include full depth reconstruction of Ferry, Depot Street and Maple Avenue in the vicinity of the bridge, construction of a sidewalk and wheelchair ramps, reconstruction and relocation of driveways, and incidental landscaping work.
Location:
  • Town of Grafton
  • Resident Engineer: Anthony Gleason
    Construction Contract Value: $1,802,041.80
    Construction Bid Price: $1,572,107.00
    Initial Construction Estimate: $1,364,299.00
    District: District 3
    Current Status: Installing drainage catch basin and drainage pipe. Placing footing for the stone wall and building the wall. (as of 07/18/2005)

    Contracts (2) Progress
    # 35657 -- Construction Contract
    Bridge Replacement G-08-012 (Steel) - Depot Street over Providence & Worcester Railroad in the Town of Grafton Completed
    # 96054 -- Design -- Bridge Open End
    RD 3 F/A NON-NHS BRIDGES-CON E Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/18/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Installing drainage catch basin and drainage pipe. Placing footing for the stone wall and building the wall.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/22/1997
    Project Review Committee PRC Approved 01/13/1998
    Project Status Advertised 09/13/2003
    Project Management
    100% Design 100% Package Received 02/01/2002
    100% Design 100% Package Comments to DE 01/23/2003
    100% Design 100% Plans Approved 04/03/2003
    25% Design 25% Package Received 07/26/1999
    25% Design 25% Package Comments to DE 10/08/1999
    25% Design 25% Package Approved 04/13/2000
    25% Design Design Public Hearing 05/24/2000
    75% Design 75% Package Received 04/04/2001
    75% Design 75% Package Comments to DE 07/31/2001
    Final Design PS&E Received 04/23/2003
    Final Design PS&E to FAPRO 08/12/2003