Project Description:
EASTHAMPTON- INTERSECTION IMPROVEMENTS @ POMEROY MEADOW ROAD, LOUDVILLE ROAD, GLENDALE STREET, WEST STREET (0.62 MILE)
This project begins on Pomeroy Meadow Road in Easthampton and extends in a northeasterly direction along Pomeroy Meadow Road, crossing the intersection of Glendale Road and Loudville Road, and continuing along West Street. This project also includes a portion of Loudville Road in a generally southeasterly direction. There will improvements to alignments, roadway sight distance and grading with a minimal impact to driveways for existing homes in the area.
Location:
  • Town of Easthampton
  • Resident Engineer: Victoria Hayes
    Construction Contract Value: $2,568,680.00
    Construction Bid Price: $2,576,952.50
    Initial Construction Estimate: $2,719,656.50
    District: District 2

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77971 -- Construction Contract
    Roadway Reconstruction and Related Work at the Intersection of Pomeroy Meadow and Loudville Roads and Glendale and West Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/17/2013
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/02/1997
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/27/2005
    Project Status Initiated 11/28/2005
    Project Status Advertised 06/22/2013
    Project Management
    100% Design 100% Package Received 01/11/2013
    100% Design 100% Package Comments to DE 02/25/2013
    25% Design 25% Package Received 07/04/2006
    25% Design 25% Package Comments to DE 04/03/2008
    25% Design 25% Package Comments to DE 10/10/2008
    25% Design Design Public Hearing 03/11/2009
    75% Design 75% Package Received 02/17/2010
    75% Design 75% Package Comments to DE 03/03/2010
    Final Design PS&E Received 05/24/2013
    Final Design PS&E to FAPRO 06/19/2013
    Consultant Contract Process NTP Issued 09/15/2005