BELLINGHAM- RECONSTRUCTION & SIGNAL UPGRADES ON PULASKI BOULEVARD, FROM MOODY STREET TO FRANKLIN T.L., INCLUDES REHAB OF B-06-012, PULASKI BOULEVARD OVER PETER'S RIVER
The purpose of this project is to improve traffic safety and operations for motorists and pedestrians. The proposed improvements for Pulaski Boulevard include widening the roadway, rehabilitating the pavement, improving the signals, and providing pedestrian safety improvements. This project includes the intersection of Wrentham Road and Paine Street for a total project length of 2.2 miles.
Location:
  • Town of Bellingham
  • Resident Engineer: Webster Larkin Sr
    Construction Contract Value: $10,511,763.68
    Construction Bid Price: $8,483,493.30
    Initial Construction Estimate: $11,192,000.00
    District: District 3

    Contracts (1) Progress
    # 61909 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Replacement of Bridge B-06-12) on a Section of Pulaski Boulivard. (ARRA Project) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/28/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/05/1998
    Project Review Committee PRC Approved 01/13/1998
    Project Review Committee Resubmitted 03/01/2005
    Project Status Advertised 12/19/2009
    Project Management
    100% Design 100% Package Received 12/04/2008
    100% Design 100% Package Comments to DE 04/28/2009
    25% Design 25% Package Received 08/30/2002
    25% Design 25% Package Comments to DE 05/21/2003
    25% Design Design Public Hearing 08/10/2005
    75% Design 75% Package Received 02/16/2007
    75% Design 75% Package Comments to DE 07/23/2007
    75% Design 75% Plans Approved 04/14/2008
    Final Design PS&E Received 10/09/2009