Project Description:
EASTHAM- WELLFLEET- TRAFFIC SAFETY IMPROVEMENT PROJECT AT 5 LOCATIONS ALONG ROUTE 6
EASTHAM- WELLFLEET- TRAFFIC SAFETY IMPROVEMENT PROJECT AT 5 LOCATIONS ALONG ROUTE 6
Location:
  • Town of Eastham
  • Town of Wellfleet
  • Resident Engineer: Paul Burns
    Construction Contract Value: $1,089,661.93
    Construction Bid Price: $1,038,839.00
    Initial Construction Estimate: $996,181.25
    District: District 5

    Contracts (2) Progress
    # 30202 -- Design -- Traffic Signing/Signals
    Statewide - Traffic engineering services with traffic signal improvement projects. Final
    # 32251 -- Construction Contract
    Traffic Safety Improvements at 5 Locations along Route 6. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/15/2002
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/06/1998
    Project Review Committee PRC Approved 04/18/1998
    Project Status Advertised 12/01/2001
    Project Management