Project Description:
FRAMINGHAM- BRIDGE REPLACEMENT, BR# F-07-006, ROUTE 9 OVER THE SUDBURY RIVER
This project proposes to replace the Route 9 Bridge over the Sudbury River and includes minor incidental roadway work.
Location:
  • Town of Framingham
  • Resident Engineer: Scott Kallin
    Construction Contract Value: $5,691,096.82
    Construction Bid Price: $4,672,650.00
    Initial Construction Estimate: $3,479,178.00
    District: District 3

    Contracts (2) Progress
    # 45564 -- Construction Contract
    Framingham - Bridge Replacment - (Steel) Route 9 over the Sudbury River Completed
    # 98405 -- Design -- Bridge Rehab/Recon/New Const
    Framingham - Rte 9 over Sudbury River F-07-006 Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/16/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/12/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 09/30/2005
    Project Management
    100% Design 100% Package Received 03/14/2005
    100% Design 100% Package Comments to DE 06/02/2005
    25% Design 25% Package Received 10/01/2002
    25% Design 25% Package Comments to DE 04/01/2003
    25% Design Design Public Hearing 03/15/2003
    75% Design 75% Package Received 12/01/2003
    75% Design 75% Package Comments to DE 12/15/2004
    Final Design PS&E Received 08/18/2005
    Final Design PS&E to FAPRO 08/18/2005