Project Description:
FALMOUTH- BRIDGE REPLACEMENT, BR# F-03-019 MEADOW NECK ROAD OVER THE MOONAKIS RIVER
Location:
  • Town of Falmouth
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $964,067.94
    Construction Bid Price: $861,489.20
    Initial Construction Estimate: $821,000.00
    District: District 5

    Contracts (1) Progress
    # 33203 -- Construction Contract
    Bridge Replacement F-03-019 (Concrete) - Meadow Neck Road over the Moonakis River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/30/2003
    Contract Information
    Project Designer: In-House Boston
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/17/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 09/07/2002
    Project Management