Project Description: |
HOLYOKE- BRIDGE REPLACEMENT, H-21-016, LYMAN STREET OVER SECOND LEVEL CANAL
The work consists of the replacement of the Lyman Street Bridge over the Second Level Canal. The new bridge will be built on the existing alignment. The bridge will be closed to traffic during construction but it will be open for pedestrians crossing. The overall length and width of the bridge will remain unchanged. The project will include roadway work at the approaches to the bridge.
|
Location: |
|
Resident Engineer: | James White |
Construction Contract Value: | $5,477,154.00 |
Construction Bid Price: | $4,877,777.00 |
Initial Construction Estimate: | $4,349,076.00 |
District: | District 2 |
|
Bridges
|
|
|
|
|