Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NORTHAMPTON- BRIDGE REPLACEMENT, BR# N-19-023, BLISS STREET OVER THE MILL RIVER
Location:
  • City of Northampton
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: Municipality
    Project Manager: Luciano Rabito
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 06/12/2004 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/19/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 06/12/2004
    Project Management
    100% Design 100% Package Received 09/10/2002
    25% Design 25% Package Received 06/28/2000
    25% Design 25% Package Approved 04/08/2004
    75% Design 75% Package Received 05/29/2002
    75% Design 75% Plans Approved 06/28/2002
    Final Design PS&E Received 07/11/2003
    Final Design PS&E to FAPRO 07/11/2003