Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BROCKTON- BRIDGE REPLACEMENT, BR# B-25-059 SPRING STREET OVER SALISBURY BROOK
Location:
  • City of Brockton
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $757,940.21
    Construction Bid Price: $608,958.00
    Initial Construction Estimate: $593,100.00
    District: District 5

    Contracts (1) Progress
    # 34059 -- Construction Contract
    Bridge Replacement B-25-59 (Concrete) - Spring Street over Salisbury Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/31/2003
    Contract Information
    Project Designer: In-House Boston
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/20/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 07/19/2003
    Project Management