Project Description:
BRIMFIELD- BRIDGE REPLACEMENT, B-24-006, ST ROUTE 19 (WALES ROAD) OVER MILL BROOK INCLUDING REPAIR OF ABUTMENT
The proposed project will replace the superstructure of the bridge carrying Route 19 (Wale Road) over the Mill Brook. The new superstructure will consist of precast spread box beams with a reinforced concrete deck and bituminous wearing surface. The new structure will span behind a portion of the existing abutments to be retained for scour countermeasures. Two stages of construction will maintain traffic across the bridge.
Location:
  • Town of Brimfield
  • Resident Engineer: Mark Shea
    Construction Contract Value: $2,252,910.00
    Construction Bid Price: $1,954,096.00
    Initial Construction Estimate: $3,043,728.00
    District: District 2

    Contracts (7) Progress
    # 34492 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 5 - Contract C Final
    # 36806 -- Design -- Footprint Bridge contracts
    (Footprint 5 Preservation) Perform design of deficient State and/or municipally owned bridges as part of the Bridge Rehabilitation/reconstruction Preservation Program. Final
    # 55040 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 59043 -- Design -- Bridge Open End
    Work will consist of statewide bridge design for the Accelerated Bridge Program on an open end basis. Final
    # 65709 -- Construction Contract
    Bridge Replacement (B-24-006) (Concrete) – Route 19 (Wales Road) over Mill Brook. (ABP) Completed
    # 68384 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/29/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/06/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Review Committee PRC Approved 09/14/2006
    Project Status Advertised 06/26/2010
    Project Management
    25% Design 25% Package Received 01/06/2009
    25% Design 25% Package Comments to DE 05/09/2009
    25% Design Design Public Hearing 06/18/2009
    25% Design 25% Plans Complete 06/30/2009
    75% Design 75% Package Received 12/23/2009
    75% Design 75% Package Comments to DE 02/05/2010
    Final Design PS&E Received 05/28/2010
    Final Design PS&E to FAPRO 06/23/2010
    Consultant Contract Process Scope to DE 10/20/2006
    Consultant Contract Process NTP Issued 10/24/2008