Project Description:
BECKET- MIDDLEFIELD- BRIDGE REPLACEMENT, BR# B-03-036=M-19-005 BANCROFT ROAD OVER WEST BRANCH OF THE WESTFIELD RIVER
The proposed bridge will be constructed adjacent to the existing bridge and will measure 29.5 feet wide and 114.8 feet long. The new structure will consist of a composite high strength concrete deck supported by four prestressed concrete New England Bulb Tee girders. The roadway will be realigned to accommodate the new bridge. The work also includes full depth reconstruction of the roadway approaches for a total combined length of 950 feet. The existing bridge will remain open during construction of the new bridge.
Location:
  • Town of Becket
  • Town of Middlefield
  • Resident Engineer: Stephen Brzezinski
    Construction Contract Value: $1,515,597.00
    Construction Bid Price: $1,332,724.60
    Initial Construction Estimate: $1,114,909.00
    District: District 1
    Current Status: The contractor is doing punch list items. Final landscaping will be done in the spring. (as of 11/17/2006)

    Contracts (1) Progress
    # 39036 -- Construction Contract
    Footprint Bridge Project - Becket/Middlefield Bancroft rd./Town Hill Rd. over the West Branch of the Westfield River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/14/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The contractor is doing punch list items. Final landscaping will be done in the spring.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/23/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 08/28/2004
    Project Management
    100% Design 100% Package Received 05/07/2004
    Final Design PS&E Received 08/02/2004
    Final Design PS&E to FAPRO 08/02/2004