IPSWICH- BRIDGE REPLACEMENT, I-01-007, ROUTE 1A (HIGH STREET) OVER THE MBTA & B&M RAILROAD
Along with replacing the bridge, the proposed work also consists of paving approach roadways, installing new drain lines and catch basins; resetting existing curb; constructing cement sidewalks on both sides of the bridge; constructing cement concrete retaining walls; installing guardrail; removing and resetting signs; and providing a temporary pedestrian crossing next to the bridge during construction.
Location:
  • Town of Ipswich
  • Resident Engineer: Thomas Callery
    Construction Contract Value: $9,811,877.00
    Construction Bid Price: $7,782,797.50
    Initial Construction Estimate: $8,257,697.00
    District: District 4

    Contracts (2) Progress
    # 51304 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 61463 -- Construction Contract
    Bridge Replacement (I-01-007) (Steel) - Route 1A (High Street) over the MBTA & B & M Railroads. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/08/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/25/1998
    Project Review Committee PRC Tabled 04/14/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 09/26/2009
    Project Management
    100% Design 100% Package Received 01/17/2007
    100% Design 100% Package Received 08/11/2009
    100% Design 100% Package Comments to DE 12/10/2007
    100% Design 100% Package Comments to DE 07/17/2009
    100% Design 100% Package Comments to DE 08/31/2009
    25% Design 25% Package Received 05/04/1999
    25% Design Design Public Hearing 07/13/1999
    75% Design 75% Package Received 12/29/2002
    75% Design 75% Package Comments to DE 09/02/2004
    Final Design PS&E Received 08/24/2009
    Final Design PS&E to FAPRO 09/23/2009
    Consultant Contract Process Scope to DE 06/16/1998
    Consultant Contract Process NTP Issued 10/05/1998