Project Description:
|
IPSWICH- BRIDGE REPLACEMENT, I-01-007, ROUTE 1A (HIGH STREET) OVER THE MBTA & B&M RAILROAD
Along with replacing the bridge, the proposed work also consists of paving approach roadways, installing new drain lines and catch basins; resetting existing curb; constructing cement sidewalks on both sides of the bridge; constructing cement concrete retaining walls; installing guardrail; removing and resetting signs; and providing a temporary pedestrian crossing next to the bridge during construction.
|