| Project Description: |
ADAMS- BRIDGE REPLACEMENT, BR# A-04-027, EAST HOOSAC STREET OVER MILLER BROOK
The purpose of this project is to replace the existing bridge with a new bridge along the existing alignment. Traffic will be maintained during construction through the provision of a temporary signal to alternate traffic flow.
|
| Location: |
|
| Resident Engineer: | Russell Duval![]() |
| Construction Contract Value: | $759,894.00 |
| Construction Bid Price: | $675,540.20 |
| Initial Construction Estimate: | $641,193.29 |
| District: | District 1 |
|
Bridges
|
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||