Project Description:
FITCHBURG- TRAFFIC SAFETY IMPROVEMENTS AT THE INTERSECTION OF MAIN STREET (ROUTE 2A) AND NORTH STREET
Location:
  • City of Fitchburg
  • Resident Engineer: Lisa Spezzaferro-Pelleti
    Construction Contract Value: $421,876.00
    Construction Bid Price: $268,705.00
    Initial Construction Estimate: $279,623.50
    District: District 3
    Current Status: Traffic signals at Main and North Streets remain on flashing status due to a request by the City of Fitchburg. (as of 06/20/2005)

    Contracts (1) Progress
    # 33274 -- Construction Contract
    Traffic Safety Improvements at the Intersection of Main and North Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/27/2003
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Traffic signals at Main and North Streets remain on flashing status due to a request by the City of Fitchburg.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/26/1998
    Project Review Committee PRC Tabled 04/14/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 10/05/2002
    Project Management