Project Description:
BROCKTON- SIGNAL & INTERSECTON IMPROVEMENTS AT ROUTE 28 (MONTELLO STREET) & ROUTE 37 (HOWARD STREET)
This project will improved traffic operation and safety by reconstructing the approaches to intersection of N. Montello St. @ Howard and Albion Sts. including sidewalks, roadway surfaces, channelization islands, pavement markings and signage. Existing traffic signal system will be replaced with a new signal system which includes ped signals and emergency vehicle preemption.
Location:
  • City of Brockton
  • Resident Engineer: Ronald Strangfeld
    Construction Contract Value: $931,384.49
    Construction Bid Price: $664,610.25
    Initial Construction Estimate: $525,448.25
    District: District 5

    Contracts (1) Progress
    # 35828 -- Construction Contract
    Intersection Improvements at Route 28 (Montello Street) and Route 37 (Howard Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/05/2004
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/27/1997
    Project Review Committee PRC Tabled 04/14/1998
    Project Review Committee PRC Denied 07/20/1998
    Project Status Advertised 07/17/2004
    Project Management
    100% Design 100% Package Received 04/21/2004
    25% Design 25% Package Received 01/06/2003
    25% Design Design Public Hearing 02/27/2002
    75% Design 75% Package Received 09/26/2003
    Final Design PS&E Received 07/08/2004
    Final Design PS&E to FAPRO 07/08/2004