Project Description:
ORLEANS- TRAFFIC SAFETY IMPROVEMENTS ON ROUTE 6A AT WEST ROAD AND ELDRIDGE PARK WAY (SKAKET CORNERS)
The work to be done under this contract consists of roadway widening, full-depth reconstruction, geometric improvements, sidewalk construction, wheelchair ramps, and other incidental items.
Location:
  • Town of Orleans
  • Resident Engineer: Paul Burns
    Construction Contract Value: $962,676.40
    Construction Bid Price: $894,916.40
    Initial Construction Estimate: $758,555.75
    District: District 5

    Contracts (1) Progress
    # 34553 -- Construction Contract
    Traffic Safety Improvements on Route 6A at Skaket Corners. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/24/2004
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/04/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 09/27/2003
    Project Management