Project Description:
CARVER- MIDDLEBOROUGH- BRIDGE REPLACEMENT, C-04-004=M-18-025, ROCHESTER ROAD OVER WEWEANTIC RIVER
The Rochester Road bridge was originally constructed in 1924 as a two-span reinforced concrete T-beam structure. The bridge is now structurally deficient and will be replaced with a new bridge which will accommodate two 11 foot travel lanes and two 2 foot shoulders. The length of the proposed single span bridge will be 66 feet, which carries Rochester Road over the Weweantic River in the Towns of Carver and Middleborough. The Rochester Road bridge replacement also involves full depth reconstruction of approximately 280 feet north and 45 feet south of the bridge along Rochester Road. Also included is the reconstruction of the intersection of Rochester Road, East Street, and Pine Street for a distance of 220 feet west and 150 feet east. The work also includes clearing and grubbing, installation of guardrail, construction of a sidewalk and wheelchair ramps, drainage improvements, pavement marking and construction of retaining walls of approximately 100 feet from each of the north bridge wing walls and one extending approximately 60 around from the southeast wing wall. The total length of the project will be approximately 924 feet. The bridge will be closed during construction and a temporary detour will be provided for abutters. Temporary and/or permanent construction easements will be required.
Location:
  • Town of Carver
  • Town of Middleborough
  • Construction Begins: Summer 2018
    Resident Engineer: Trevor O'Bryan
    Construction Bid Price: $2,656,217.75
    District: District 5

    Contracts (2) Progress
    # 102270 -- Construction Contract
    Bridge Replacement Br. No. C-04-004=M-18-025 (NEXT D Beams) Rochester Road over Weweantic River including Intersection Reconstruction at East and Pine Streets. Completed
    # 86005 -- Design -- Services
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/22/2018
    Contract Information
    Project Designer:
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/09/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 09/16/2017
    Project Management
    100% Design 100% Package Received 05/19/2017
    100% Design 100% Package Comments to DE 06/23/2017
    100% Design 100% Package Received - Resub 1 07/14/2017
    100% Design 100% Plans Approved 05/19/2017
    100% Design 100% Plans Complete 05/19/2017
    25% Design 25% Package Received 11/21/2016
    25% Design 25% Package Comments to DE 12/21/2016
    25% Design Design Public Hearing 01/24/2017
    25% Design 25% Plans Complete 11/21/2016
    75% Design 75% Package Received 05/19/2017
    75% Design 75% Package Comments to DE 06/23/2017
    75% Design 75% Plans Approved 05/19/2017
    75% Design 75% Plans Complete 05/19/2017
    Final Design PS&E Received 07/28/2017
    Final Design PS&E to FAPRO 09/01/2017