PALMER- RECONSTRUCTION OF MAIN STREET FROM SYKES STREET TO HIGH STREET INTERSECTION
The project length is 0.6 miles and the work consists of cold planing and overlay reconstruction, traffic signal improvements, granite curb installation, cement concrete sidewalk construction, drainage system improvements and pavement markings.
Location:
  • Town of Palmer
  • Resident Engineer: Joseph Borowiec
    Construction Contract Value: $1,014,020.00
    Construction Bid Price: $876,382.00
    Initial Construction Estimate: $795,590.00
    District: District 2
    Current Status: Physical work completed. (as of 12/13/2006)

    Contracts (1) Progress
    # 41598 -- Construction Contract
    Palmer - Roadway Reconstruction and Related Work on a Section of Main Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/28/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work completed.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/13/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 02/19/2005
    Project Management
    100% Design 100% Package Received 04/04/2002
    100% Design 100% Package Comments to DE 05/14/2002
    25% Design 25% Package Received 08/19/1999
    25% Design 25% Package Comments to DE 11/30/1999
    25% Design Design Public Hearing 03/01/2000
    75% Design 75% Package Received 01/10/2001
    75% Design 75% Package Comments to DE 03/15/2001
    Final Design PS&E Received 06/03/2004
    Final Design PS&E to FAPRO 06/03/2004