Project Description:
PALMER- RECONSTRUCTION & IMPROVEMENTS OF SPRINGFIELD STREET, FROM THE WILBRAHAM T.L. EASTERLY TO BRIDGE STREET
1.25 miles of Springfield Street will be reconstructed. Also included in the project are the signalization of the Main and Bridge Street intersection. Springfield Street will be widened to 33 feet and consists of two 11.5 foot travel lanes and two 5 foot shoulders. A 5 foot cement concrete sidewalk on the south side is proposed for the entire length with an additional 5 foot grass strip proposed, between the curb and sidewalk, along some sections. The proposed work consists of excavation by cold planer, hot mix asphalt overlay, earth excavation, full depth hot mix asphalt pavement construction, drainage system improvements, hot mix asphalt berm installation, sidewalk and wheelchair ramp construction, granite curb installation, hot mix asphalt and gravel driveway construction, waterline replacement, abandoned track removal, pavement markings, signing, landscaping, and other incidental items necessary to complete the required work.
Location:
  • Town of Palmer
  • Resident Engineer: Mark Shea
    Construction Contract Value: $3,535,110.43
    Construction Bid Price: $3,103,924.30
    Initial Construction Estimate: $4,248,154.00
    District: District 2

    Contracts (1) Progress
    # 58224 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Springfield Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/08/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/13/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 12/20/2008
    Project Management
    100% Design 100% Package Received 04/19/2006
    100% Design 100% Package Comments to DE 03/15/2007
    25% Design 25% Package Received 10/04/1999
    25% Design 25% Package Comments to DE 01/03/2000
    25% Design Design Public Hearing 03/15/2000
    75% Design 75% Package Received 10/29/2001
    75% Design 75% Package Comments to DE 04/03/2002
    Final Design PS&E Received 12/10/2008
    Final Design PS&E to FAPRO 12/10/2008