Project Description:
ASHFIELD- BRIDGE REPLACEMENTS, BR# A-13-004, ROUTE 116 OVER THE SOUTH RIVER & A-13-012, ROUTE 116 OVER THE SOUTH RIVER
The work includes furnishing all necessary labor, materials and equipment required for the demolition, removal and disposal of the existing superstructures, and constructing new 12.0 meter and 10.0 meter long single span bridges. The work for each bridge also includes the construction of the proposed superstructure and substructure, including the steel bridge railings, end posts, precast reinforced concrete rigid frame structure units with roof slabs and walls, wingwalls, reinforced concrete footings, approach slabs, roadway approaches, a temporary Acrow Panel Bridging System including its foundation and the associated roadway work.
Location:
  • Town of Ashfield
  • Resident Engineer: Russell Duval
    Construction Contract Value: $2,002,463.00
    Construction Bid Price: $1,809,592.94
    Initial Construction Estimate: $1,333,959.00
    District: District 1
    Current Status: Both bridges are open to traffic and only punch list items remain. (as of 07/27/2007)
    Additional Info: Temporary traffic signals are in place with one lane alternating traffic at both bridges. (as of 04/28/2006)

    Contracts (2) Progress
    # 30277 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 42947 -- Construction Contract
    Ashfield - Bridge Replacement (A-13-4 & A-13-12) Route 116 over the South River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/22/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Both bridges are open to traffic and only punch list items remain.
    Additional Info
    Temporary traffic signals are in place with one lane alternating traffic at both bridges.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/21/2000
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 09/18/2004
    Project Management
    100% Design 100% Package Received 08/12/2004
    25% Design 25% Package Received 03/13/2002
    25% Design Design Public Hearing 04/24/2002
    25% Design 25% Plans Complete 04/06/2004
    75% Design 75% Package Received 06/22/2004
    75% Design 75% Plans Approved 07/19/2004
    Final Design PS&E Received 09/03/2004
    Final Design PS&E to FAPRO 09/03/2004