PLYMOUTH- BRIDGE REPLACEMENT, BR# P-13-012 RIVER STREET OVER EEL RIVER
Location:
  • Town of Plymouth
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $878,789.02
    Construction Bid Price: $852,920.55
    Initial Construction Estimate: $629,000.00
    District: District 5

    Contracts (1) Progress
    # 33066 -- Construction Contract
    Bridge Replacement P-13-012 (Concrete)- River Street over Eel River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/18/2002
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/24/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 12/01/2001
    Project Status Advertised 06/15/2002
    Project Management