Project Description:
SPRINGFIELD- BRIDGE REPLACEMENTS, S-24-090 & S-24-091, ROOSEVELT AVENUE OVER CONRAIL SPUR & MAIN (DOUBLESTACK) LINE
The work under this project consists of the replacement of the Roosevelt Avenue Bridges over the Conrail Main Line and over the Conrail Spur Line. The proposed structure over the Main Line (near Bay Street) will be a three-span steel beam superstructure with a reinforced concrete deck. The approach roadways will be fully reconstructed and the profile will be slightly raised to achieve the required minimum vertical railroad clearance. The proposed structure over the Spur Line (near Cottage Street) will be a single span steel beam superstructure with a reinforced concrete deck. The bridge widths and the horizontal alignments of both bridges will remain essentially the same. Both bridges will be constructed in phases in order to maintain one lane of traffic in each direction. The addition of a sidewalk is proposed for the west side of the bridges on Roosevelt Avenue as a result of the recent private development in the area.
Location:
  • City of Springfield
  • Resident Engineer: Joseph Hogan
    Construction Contract Value: $8,451,349.00
    Construction Bid Price: $7,493,403.00
    Initial Construction Estimate: $8,972,315.00
    District: District 2

    Contracts (2) Progress
    # 43179 -- Design -- Hwy Eng Open End
    Layout Section requires a consultant to provide the service of Layout plan and written description preparation. Final
    # 68223 -- Construction Contract
    2 Bridge Replacement (S-24-091 & S-24-290) (Steel) - Roosevelt Avenue over the CSX Main (Doublestack) and Spur Lines. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/21/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/03/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 03/05/2011
    Project Management
    100% Design 100% Package Received 05/28/2009
    100% Design 100% Package Comments to DE 08/04/2009
    25% Design 25% Package Received 02/19/2003
    25% Design 25% Package Comments to DE 07/21/2003
    25% Design Design Public Hearing 05/12/2004
    75% Design 75% Package Received 09/13/2004
    75% Design 75% Package Received 11/03/2008
    75% Design 75% Package Comments to DE 05/09/2005
    75% Design 75% Package Comments to DE 03/31/2009
    Final Design PS&E Received 08/02/2010
    Final Design PS&E to FAPRO 10/12/2010
    Consultant Contract Process Scope to DE 07/07/1999
    Consultant Contract Process NTP Issued 11/24/2000