Project Description:
HANOVER- RECONSTRUCTION OF WASHINGTON STREET (ROUTE 53) & RELATED WORK, FROM THE ROUTE 3 (NB) RAMP TO WEBSTER STREET (ROUTE 123)
The proposed project constitutes the final phase of the overall Route 53 reconstruction project. Work on this project includes minor widening of Route 53 and the installation of sidewalks from approximately 400 feet north of the Route 3 NB ramp to Route 123. Bicycle accommodations consisting of a usable shoulder have been provided in accordance with applicable design guides.
Location:
  • Town of Hanover
  • Resident Engineer: Peter Benkart
    Construction Contract Value: $1,570,926.62
    Construction Bid Price: $1,372,444.66
    Initial Construction Estimate: $1,376,000.00
    District: District 5

    Contracts (4) Progress
    # 54138 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69360 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 85006 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Route 53 (Washington Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/10/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/31/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Review Committee Letter 07/19/2006
    Project Status Advertised 09/20/2014
    Project Management
    100% Design 100% Package Received 01/02/2014
    100% Design 100% Package Comments to DE 03/12/2014
    25% Design 25% Package Received 10/13/2009
    25% Design 25% Package Comments to DE 12/13/2012
    25% Design Design Public Hearing 09/24/2013
    75% Design 75% Package Received 01/02/2014
    75% Design 75% Package Comments to DE 03/12/2014
    Final Design PS&E Received 04/25/2014
    Final Design PS&E to Peer Reviewer 05/05/2014
    Final Design Peer Review Comments to DE 06/18/2014
    Final Design PS&E to FAPRO 09/17/2014
    Consultant Contract Process Scope to DE 06/28/2012
    Consultant Contract Process NTP Issued 08/14/2012