Project Description:
MIDDLEBOROUGH- SIGNAL & INTERSECTION IMPROVEMENTS AT ROUTE 105 & ROUTE I-495 RAMPS
This project will enhance safety and improve the efficiency of the traffic flow by installing new coordinated traffic signals at the intersection of Route 105 (North Main Street) and the two I-495 ramp systems (for I-495 Northbound and I-495 Southbound). This work will include adding turn lanes on both the ramps and Route 105; a closed loop signal system for Route 105 from Bridge St. to Route 28; and geometric improvements at the intersection of Route 105 and East Clark Road. The work on Route 105 is expected to extend from Commercial St. to approximately 400 feet south of Route 28. A key element of this project includes coordinating with the Lakeville Hospital Redevelopment, the Route 79 relocation, and the Route 105/Route 28 projects.
Location:
  • Town of Middleborough
  • Resident Engineer: April Letourneau
    Construction Contract Value: $3,156,785.00
    Construction Bid Price: $2,481,401.50
    Initial Construction Estimate: $2,915,163.17
    District: District 5

    Contracts (3) Progress
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 71093 -- Construction Contract
    Intersection Improvements and Related Work (Including Traffic Signals) at the Route 105 (South Main Street) to Interstate 495 Ramps. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/16/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/31/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 09/17/2011
    Project Management
    100% Design 100% Package Received 08/05/2011
    100% Design 100% Package Comments to DE 09/01/2011
    25% Design 25% Package Received 06/24/2010
    25% Design 25% Package Comments to DE 12/07/2010
    25% Design Design Public Hearing 01/05/2011
    75% Design 75% Package Received 03/29/2011
    75% Design 75% Package Comments to DE 06/24/2011
    Final Design PS&E Received 09/09/2011
    Final Design PS&E to FAPRO 09/12/2011
    Consultant Contract Process Scope to DE 01/28/2010
    Consultant Contract Process NTP Issued 04/16/2010