Project Description:
RAYNHAM- SIGNAL IMPROVEMENTS @ ROUTE 138 AND ROUTE I-495 RAMPS
This project consists of the final design of traffic signals at the interchange of the I-495 ramp junctions with Route 138 in Raynham, Massachusetts. The ramp junctions at this diamond interchange are currently unsignalized. No geometric changes are anticipated at this time.
Location:
  • Town of Raynham
  • Resident Engineer: John Bielski
    Construction Contract Value: $953,932.31
    Construction Bid Price: $813,190.21
    Initial Construction Estimate: $947,883.50
    District: District 5

    Contracts (3) Progress
    # 45688 -- Design -- Hwy Eng Open End
    Work will generally consist of providing engineering design and review services to the Projects Division on an open end basis for various statewide highway and bridge projects Final
    # 48664 -- Design -- Traffic Signing/Signals
    Work will generally consist of preparing Plans, Specs and Estimate for intersection improv. and traffic signal installations associated with the Hwy Safety Improv. Prg (HSIP). Final
    # 57033 -- Construction Contract
    RAYNHAM- Intersection Improvements on Route 138 (Broadway) at the I-495 Ramps Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/12/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/31/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 08/16/2008
    Project Management
    100% Design 100% Package Received 06/11/2008
    100% Design 100% Package Comments to DE 07/18/2008
    25% Design 25% Package Received 06/27/2006
    25% Design 25% Package Comments to DE 10/02/2006
    25% Design Design Public Hearing 12/13/2006
    75% Design 75% Package Received 09/28/2007
    75% Design 75% Package Comments to DE 02/07/2008
    Final Design PS&E Received 08/06/2008
    Final Design PS&E to FAPRO 08/12/2008
    Consultant Contract Process NTP Issued 06/04/2004