Project Description:
SEEKONK- INTERSECTION IMPROVEMENTS AT ROUTE 114A, ARCADE AVENUE & MILL ROAD, INCLUDES REHAB OF CULVERT S-08-004 OVER RUNNINS RIVER
Work on this project includes intersection improvements at Route 114A, Arcade Avenue and Mill Road. Arcade Avenue will be realigned with Route 114A to reduce the skewed alignment of the intersection. Also included in the work will be the installation of traffic signals, the construction of pedestrian sidewalks, and drainage improvements. Includes the rehabilitation of culvert s-08-004 over the Runnins River.
Location:
  • Town of Seekonk
  • Resident Engineer: Marc Cardinal
    Construction Contract Value: $3,217,432.74
    Construction Bid Price: $2,487,166.00
    Initial Construction Estimate: $2,321,000.00
    District: District 5

    Contracts (3) Progress
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 84663 -- Construction Contract
    Intersection Improvements and Related Work at Fall River and Arcade Avenue Including Bridge Rehabilitation Br. No. S-08-004 (Pre-Cast Arch) Fall River Avenue (Route 114A) over Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/28/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/03/1998
    Project Review Committee PRC Tabled 07/20/1998
    Project Review Committee PRC Approved 10/20/1998
    Project Status Advertised 09/06/2014
    Project Management
    100% Design 100% Package Received 07/14/2014
    100% Design 100% Package Comments to DE 08/18/2014
    25% Design 25% Package Received 03/08/2013
    25% Design 25% Package Comments to DE 06/03/2014
    25% Design 25% Package Comments to DE 06/27/2014
    25% Design 25% Package Rejected 09/12/2012
    25% Design Design Public Hearing 06/05/2013
    75% Design 75% Package Received 03/18/2014
    75% Design 75% Package Comments to DE 05/08/2014
    75% Design 75% Plans Approved 05/16/2014
    Final Design PS&E Received 08/29/2014
    Final Design PS&E to FAPRO 09/03/2014
    Consultant Contract Process NTP Issued 12/19/2011