READING- SIGNALIZATION & IMPROVEMENTS ON ROUTE 28 (MAIN STREET) FROM WASHINGTON STREET TO ROUTE 129 (INCLUDES PORTIONS OF ASH STREET, LOWELL STREET & HARDEN STREET)
Improvements include pavement rehabilitation, roadway geometry and traffic signals. The proposed sidewalks and streetscape enhancements of ornamental lighting, trees, and brick pavers will improve overall pedestrian and vehicular safety in the Reading downtown businesss area.
Location:
  • Town of Reading
  • Resident Engineer: Peter Jodoin
    Construction Contract Value: $5,646,677.00
    Construction Bid Price: $5,490,864.86
    Initial Construction Estimate: $5,610,985.00
    District: District 4

    Contracts (1) Progress
    # 51620 -- Construction Contract
    Reading - Roadway Reconstruction and Related Work on a Section of Route 28 (Main Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/25/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/01/1998
    Project Review Committee PRC Tabled 04/14/1998
    Project Review Committee PRC Approved 07/20/1998
    Project Status Advertised 09/16/2006
    Project Management
    100% Design 100% Package Received 10/31/2005
    100% Design 100% Package Comments to DE 02/17/2006
    25% Design 25% Package Received 06/11/2001
    25% Design Design Public Hearing 10/23/2002
    75% Design 75% Package Received 11/05/2003
    75% Design 75% Package Comments to DE 12/02/2003
    Final Design PS&E Received 09/06/2006
    Final Design PS&E to FAPRO 09/12/2006