GARDNER- RESURFACING, GREEN STREET FROM MATTHEWS STREET NORTHERLY TO ROUTE 140
The proposed project consists of resurfacing Green Street from the intersection with Stone Street to a point 1,500 feet north of Matthews Street, a total distance of approximately 4,250 feet. The work will include full-depth roadway widening and resurfacing, sidewalk construction, drainage structure and water gate adjustment, installing bituminous and granite curb, removing and resetting granite curb, placing pavement markings and instituting traffic control operations during construction.
Location:
  • City of Gardner
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $632,341.00
    Construction Bid Price: $570,582.80
    Initial Construction Estimate: $549,794.00
    District: District 3
    Current Status: Project essentially complete except for some signage and bicycle path line painting. (as of 08/03/2006)

    Contracts (1) Progress
    # 43336 -- Construction Contract
    Gardner - Roadway Reconstruction and Related work on a Section of Green Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/16/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project essentially complete except for some signage and bicycle path line painting.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/12/1998
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 07/30/2005
    Project Management
    100% Design 100% Package Received 01/26/2005
    100% Design 100% Package Comments to DE 05/25/2005
    25% Design 25% Package Received 05/16/2001
    25% Design 25% Package Comments to DE 02/04/2003
    75% Design 75% Package Received 07/28/2003
    75% Design 75% Package Comments to DE 07/26/2004
    Final Design PS&E Received 07/19/2005
    Final Design PS&E to FAPRO 07/19/2005